The Delhi government has scheduled a construction ban for the 2026-27 winter as part of its Winter Action Plan. Dust-generating demolition and outdoor civil work are restricted in Delhi from 1 November 2026 to 31 January 2027, and all construction and demolition will stop from 10 December 2026 to 20 January 2027. The order applies to the National Capital Territory of Delhi only. Projects in Noida, Gurugram, Ghaziabad and Faridabad continue under the Graded Response Action Plan (GRAP), which halts construction only at Stage 3 or Stage 4.
Also Read: Gurugram Stilt+4 Policy: High Court Challenge Explained
Current status of construction in Delhi NCR
As of late October 2026, construction is permitted across Delhi NCR. The Commission for Air Quality Management (CAQM) invoked GRAP Stage 1 on 21 October 2026, which requires stricter dust control at sites but does not stop work. The Stage 1 rules are explained in our guide to GRAP 1 in Delhi NCR.
The main change this season is the approach. Earlier construction bans were triggered when air quality crossed a set threshold. Delhi's Winter Action Plan 2026-27 instead fixes the dates in advance, based on the period when the city's air quality is usually at its worst.
Delhi construction ban dates for winter 2026-27
Date
Measure in Delhi
1 Oct 2026
"No PUCC, No Fuel" extended to 500 camera-equipped fuel stations
1 Nov 2026
Dust-generating demolition and outdoor civil construction restricted
1 Nov 2026
50% work from home for offices; parking charges doubled
1 Nov 2026
Non-BS-VI vehicles registered outside Delhi barred from entry
10 Dec 2026
Complete ban on construction and demolition begins
20 Jan 2027
Complete ban ends; dust-generating restrictions continue
31 Jan 2027
Dust-generating restrictions and vehicle entry ban end
28 Feb 2027
Work-from-home and parking measures end
The complete ban lasts about six weeks. The window covers December and early January, when low wind speeds allow dust and smoke to accumulate over the city.
These dates set a minimum. If air quality deteriorates further outside this period, CAQM may still invoke GRAP Stage 3 or Stage 4, which would halt construction across the entire NCR, including Delhi.
Permitted and restricted activities
The Winter Action Plan works in two phases: a partial restriction on dust-generating work, followed by a complete stop.
Partial restriction: 1 November to 9 December, and 21 to 31 January
Activities that generate dust are restricted. These include demolition, excavation and outdoor civil construction. Work that does not generate dust may continue. Storing or dumping construction material outside the designated site area is prohibited throughout the season.
Complete ban: 10 December to 20 January
All construction and demolition in Delhi must stop. Official statements describe this as a complete ban and have not listed exemptions. Some industry commentary suggests that interior finishing and electrical or plumbing work may continue as non-dust activities, but no government order has confirmed this. Anyone planning work during this period should seek clarification from the relevant local body first.
Guidance for homeowners
Renovation work that involves breaking, drilling, excavation or mixing material on site should be scheduled before 1 November or after 31 January. Lighter work such as painting, wiring or furniture installation is likely to be acceptable outside the complete-ban window, subject to confirmation from the local body.
Applicability to Noida, Gurugram and other NCR cities
The Winter Action Plan is a Delhi government order and applies only within the National Capital Territory of Delhi. The position in neighbouring cities is as follows.
Noida and Greater Noida (Uttar Pradesh): no fixed-date construction ban has been announced. Projects follow GRAP. Our guide to the best sectors to live in Noida covers the city in more detail.
Gurugram (Haryana): no fixed-date ban has been announced. Haryana requires projects above 500 sq m to register on its dust-control portal and deploys anti-smog guns at major sites. Our list of under-construction projects on Dwarka Expressway covers the corridor in detail.
Ghaziabad and Faridabad: GRAP applies. The Delhi calendar does not.
The Uttar Pradesh and Haryana governments may issue separate orders later in the season. Buyers and developers outside Delhi should monitor state notifications through the winter.
Delhi Winter Action Plan and GRAP compared
Delhi Winter Action Plan
GRAP
Issued by
Delhi government
CAQM
Area covered
Delhi only
Entire NCR
Trigger
Fixed calendar dates
Daily AQI and forecasts
Complete construction stop
10 Dec to 20 Jan (scheduled)
Stage 3 or 4 only (not scheduled)
Both frameworks operate at the same time. Projects in Delhi are subject to both, while projects elsewhere in NCR are subject to GRAP alone.
Impact on homebuyers
Under-construction projects in Delhi. Possession timelines are likely to be affected. A six-week stoppage, combined with the dust restrictions before and after it, can push schedules back further than the ban itself. Remobilising labour after a winter break also takes time. DLF's management has previously stated that winter restrictions can disrupt construction for 30 to 45 days or more in a quarter. Buyers in Delhi projects such as DLF One Midtown should ask the developer how the winter calendar affects any pending work and compare the response with the project's RERA updates. Our RERA guide explains where to find them.
Under-construction projects in Noida and Gurugram. These projects fall outside the Delhi order. The relevant risk is a GRAP Stage 3 or Stage 4 order, which depends on air quality and is not certain. If a developer attributes a delay to winter restrictions, buyers can check whether GRAP was in fact raised during that period.
Ready-to-move properties. The ban does not affect completed homes. Registration, loan disbursement and possession continue as normal. In Delhi, ready options include resale flats and DDA flats in Narela, covered in our guide to flats under ₹50 lakh in Delhi NCR.
Buyers paying rent while awaiting possession. Any delay extends the period of paying rent and EMI together. Our home loan EMI table can help estimate the additional cost.
Requirements for developers and contractors
- Scheduling: dust-generating work should be completed before 1 November where possible, with finishing work planned for February onward.
- Registration and monitoring: sites above 500 sq m are monitored through Delhi's Dust Portal 2.0, launched in July 2026. Around 700 large sites are also monitored by AI-enabled cameras that alert the site owner and the department when dust levels rise.
- Material storage: storage or dumping outside the designated site area is prohibited throughout the season.
- Worker welfare: the Supreme Court has directed NCR states to pay subsistence allowance from labour cess funds to construction workers when work is halted for pollution control. Workers must be registered with the state construction welfare board to receive it, so completing registration before December is advisable.
Other measures from 1 November
The construction calendar is one part of a broader plan. The following measures also apply in Delhi:
- Offices: government and private offices must keep 50% of staff working from home on a rotational basis until 28 February 2027. Government offices also move to staggered working hours.
- Parking: charges are doubled at authorised parking sites, except Delhi Metro parking.
- Vehicle entry: vehicles registered outside Delhi that do not meet BS-VI norms are barred from entering the city until 31 January 2027. Electric, CNG and essential-service vehicles are exempt. Reports differ on whether private cars are covered, so owners of older vehicles should check the latest notification before travelling.
- Fuel: vehicles without a valid PUC certificate, or past their permitted age, are refused fuel at camera-equipped fuel stations.
For office occupiers, both the work-from-home requirement and the fit-out restrictions are relevant. Buildings such as Max House in Okhla are within Delhi, so any civil fit-out work there falls under the city's calendar. Our guide to the best locations for office space in Delhi NCR compares the main office markets.
FAQs
Is construction banned in Delhi in December 2026? Yes. All construction and demolition in Delhi is banned from 10 December 2026 to 20 January 2027 under the Delhi government's Winter Action Plan. Dust-generating work is also restricted from 1 November 2026 to 31 January 2027.
Is construction banned in Noida and Gurugram? Not under the Delhi order, which applies only within Delhi. Noida, Gurugram, Ghaziabad and Faridabad follow GRAP, which stops construction only at Stage 3 or Stage 4.
Can I renovate my flat in Delhi during the ban? Work that involves breaking, drilling or creating dust should be avoided between 1 November and 31 January. For the complete ban from 10 December to 20 January, no exemptions have been officially listed, so check with the local body before starting any work, including interior work.
Will the construction ban delay my flat's possession? For projects in Delhi with work still pending, a delay is likely, at least equal to the length of the ban and possibly longer. Projects in Noida and Gurugram are not covered by the Delhi order.
Is construction banned under GRAP 1? No. GRAP Stage 1 permits construction with strict dust control. Under GRAP, construction stops only at Stage 3 (non-essential work) or Stage 4 (all work).
Why has Delhi fixed dates for the construction ban? Pollution levels in Delhi peak at around the same time each winter. Fixed dates allow developers, workers and buyers to plan in advance instead of responding to sudden orders when the AQI rises.
This article is for general information. Dates and rules may be revised, so check the latest Delhi government and CAQM orders before planning any work.